How much concrete for a 30 × 40 slab?

A 30 × 40 ft slab (1,200 sq ft) poured 4 inches thick takes 14.81 cubic yards of concrete. With 10% extra for uneven ground and spillage, order 16.3 cubic yards of ready-mix or buy 734 bags of 80 lb mix.

Concrete for a 30 × 40 ft slab by thickness
ThicknessExact volumeOrder (+10%)80 lb bags60 lb bagsTypical use
4 in14.81 yd³16.3 yd³ (12.46 m³)734978Patio, walkway, shed floor
5 in18.52 yd³20.37 yd³ (15.57 m³)9171223Hot tub pad, light driveway
6 in22.22 yd³24.44 yd³ (18.69 m³)11001467Driveway, garage floor

Bag counts include the 10% extra and assume 0.60 ft³ per 80 lb bag and 0.45 ft³ per 60 lb bag.

Change the size, thickness or price

Concrete needed
16.3 yd³
80 lb bags
734
60 lb bags
978
40 lb bags
1467

440 cubic feet = 16.3 cubic yards = 12.46 m³. Above about 1 cubic yard, ready-mix delivery is usually cheaper and faster than bags.

Rough material cost (cheapest option)

$2,770
Ready-mix: 16.3 × price per cubic yard
$
80 lb bags: 734 × price per bag
$

Ready-mix often has a short-load fee under 4–5 yd³. Rough 2026 US prices, edit to match local quotes.

FAQ

How many bags of concrete for a 30x40 slab?

At 4 inches thick, 734 bags of 80 lb concrete mix or 978 bags of 60 lb mix, including 10% extra. At 6 inches, 1100 bags of 80 lb mix.

Should I use bags or ready-mix for a 30x40 slab?

Ready-mix is usually cheaper and much less work above about 1 cubic yard, and this slab needs 16.3. Under 4–5 yards many suppliers add a short-load fee, so compare a quote with 734 bags.

How do you calculate concrete for a 30 by 40 slab?

Multiply length × width × thickness in feet: 30 × 40 × (4 ÷ 12) = 400 cubic feet. Divide by 27 to get 14.81 cubic yards, then add 5–10% extra.

Other slab sizes